Friday, July 15, 2011

Floor and Roof progress...

The FIU perform[D]ance house is making a lot of progress as we build in the hot and rainy summer weather. Our sponsors/contractors are doing a great job as well as all the students taking part of this exciting journey.


 

Roof Plywood arriving on site!
Roof Joists



Take a look at the construction site as floor joists are being installed, roof joists, and roof plywood arriving on site.








House Frame almost ready with Floor + Roof joists in place!

Thursday, July 14, 2011

Wood for DECK arrived on Site

Wednesday July 13th the Wood for the construction of the Deck arrived on site!... The deck area is 1,500sqft, which is double the area of the interior of the house, which is aprox 800sqft. The exterior Deck will be built entirely by the students.

Alvaro, Alfonso and Cristina as they received the wood on site.

Chrissy, our construction manager as they review the Deck Shop Drawings to begin the assembly
Meet Carlos as he cuts the wood
Since the wood arrived, the students have been working on site as they begin to build each module of the deck, we will have approximately 40 modules that will come together in Washington DC to form what will be the amazing exterior space of the Perform[D]ance House.

  
Double checking the shop drawings to continue working on the deck!




Saturday, July 9, 2011

We won't let the RAIN stop us!

A few days ago, we had to shut down the job site at 10am because of the RAIN! Today the team came up with a new game plan to defeat the RAIN… The installation of a tarp over the structure of the Perform[D]ance House! It was a success and the team was able to finish installing the floor joists!

Today, we experienced heavy rain causing the tarp to fill with water and eventually collapse. The team came up with the idea of attaching 2x4's for support and it was a success, again... we won't let the rain stop us!

Tuesday, July 5, 2011

Steel Frame came together!

Today, the team tightened all bolts between the two steel frames that compose the house. These will come apart once the house is ready to be dismantled to travel to Washington DC at the beginning of September. Also, the installation of the flooring system began, as we faced rainy South Florida weather!

Thursday, June 30, 2011

WELCOME TO OUR BLOG!

Join us as we experience the last phase of the Solar Decathlon 2011 Competition! The CONSTRUCTION phase!

 Today, June 30th the steel cages were delivered to the site and the whole team is very exited to begin with the construction of the Perfom[D]ance House.

Half of the Steel Frame arriving to FIU
Meet Luis, Alvaro and Manny as they welcomed the Steel Frame to the job site!


Thursday, May 13, 2010

Saturday, May 1, 2010

Summer Schematics

Decathlon studio begins!  


We'll select our team leaders and our main areas of contribution --and then we'll get to work:  We need to produce a Schematic Design Manual and a Preliminary Cost Estimate.  Our first deliverables are due impossibly soon:  May 4th.  Didn't we just have final reviews?? 


The good news:  Field Trip!  Schematic Design Workshop ahead --in Washington DC




photo

SD team

First day....!